MEMORIAL NORTHWEST HOA 2009 BUDGET MNW General Meeting
March 2009 2009 Budget Objectives / Options
Key Assumptions
Budget Overview / Expense Analysis
2009 Budget Objectives
όBalanced budget if possible with back-up to use cash reserves
όMaintain cash reserve for ~ three / six months (rainy day fund) of annual HOA expenses
όCommunity Center options are a separate discussion
2009 Budget Key Assumptions Revenues
HOA dues flat @ $400 Historical collections ratio (~95%) ; interest income ~ dramatically reduced Community Center rentals flat / misc revenues flat (no insurance refund)
Spending increases for security / insurance / small contingencies / evaluate LT Facility Plan Security contract up 3% each year (same number of deputies) Insurance costs up 5-10%
όTennis - any major court rebuild part of LT facilities Plan όFitness flat spend (purchased new equipment in 2006 / 2007 / 2008) όPool contract slight 3% increase from last year (D&S good performance) όAssumes no major repairs for club house όElectricity rates ~ flat with 2008 actual spending (long term contract ) Long Term Facility plan process WIP
2009 Budget Overview Revenues $860,000 Expenses $860,000 Community Center ( 46% ) Security ( 27% ) Common area maintenance / pest control ( 11% ) Management Company ( 6% ) Other - Insurance, Legal, Collections, Other ( 10% ) Excess Rev / expenses $-0-
---------------------------------------------------------------------------------------------------------------------------------- For theoretical comparison only Community center surplus +$29,000 Maint Fund deficit - $29,000
2009 Revenues All other (Club rentals, etc.) 11% Assessments 89%
2009 Expenses 16% All Other
11% Maint
46% Community Center
27%Security
What is not in the 2009 Budget No major Community Center renovations / additions / repairs
( no new tennis courts or major repairs to courts # 1-4 / no re-plastering of pool or new pool (s) / no major fitness or clubhouse refurbishments or new facilities
No significant exterior entrance monument repairs or renovations such as Cul de Sacs / Sprinklers, etc.
No repairs to pillars or perimeter homeowner fence.
No major legal spend /adverse settlement on any HOA / Homeowner lawsuit(s)
Another major hurricane / damages and or extra trash pick-up
No monies built in for recoveries if we are granted non-profit 501 c 3 status
No monies from insurance proceeds from Hurricane Ike
HOA Assessments Overview Assessement No Dues Increase
Given overall economic climate no dues increase for 2009 / we have sufficient cash reserves even if the actual 2009 results are slightly worse that the planned budget @ break-even
History
2008 was the first increase in 12 years except 2005 homeowners vote to take over the Community Center
The CPI has moved up over 35%...
The 2008 increase reflected the continued inflation for security, maintenance, energy costs and administration
Community Center assessment of $175 ( 2005) was designed to be sustainable for a facility with significant catch-up refurbishments and minor phased renovations but not a major tear-down / renovation. We have delivered that assumption / the cash surplus we have run each year approximates the debt service for the original ~ $750,000 loan assumption
Memorial Northwest continues to have lower (lowest) assessments in the area
Funding for Community Center Improvements
Depending on the vote of the homeowners who may authorize a minor / major rebuild of the community center and to provide funding (if required) we would then raise assessments (if required) to repay debt required to fund minor /major renovations per that vote
Surplus / Deficit 2003 primarily due to Section 18,25 revenues
2004 primarily due to security contract reduction
2005 primarily due to Community Center one time catch-up repairs
2006 / 2007 lower / delayed Community Center spend & increased rental revenues partially offset by maint overspend / 2007 helped by $28,000 insurance settlement for roof damage
2008 primarily extra spending for Hurricane Ike
Capital Fund Activity Originally funded $200 in 1999 / Transfer surplus funds in succeeding years
1999 Stuebner Airline Entrance
2000 Champion Forest South
2001 Champion Forest North / Sprinkler project
2002 Deep Pines / Sprinkler project / Started Narmore Entrance
2003 Complete Narmore Entrance / Sec #18,25 Entrance, (no pocket park although was originally in budget)
2004 Limited spend for minor interior entrance monuments
2006 /2007/ 2008 No substantive capital spend
|